You transfer material between two plants. The goods issue in the delivering plant is already booked. During the transport process, some parts are damaged and the delivering plant is responsible for…

The correct answer is D. You reverse the stock removal in the issuing plant and post the scrapping there. See the full explanation below for the reasoning.

Question

You transfer material between two plants. The goods issue in the delivering plant is already booked. During the transport process, some parts are damaged and the delivering plant is responsible for the transportation. How can you post this scrapping?

Options

  • AYou adjust the stock in transit and put away the remaining quantity in the receiving plant.
  • BYou book the goods receipt for the entire quantity to the unrestricted use stock in the receiving
  • CYou book the goods receipt for the entire quantity to the blocked stock in the receiving plant.
  • DYou reverse the stock removal in the issuing plant and post the scrapping there.

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    11% (3)
  • D
    78% (21)