At what level can you set quantity and value updating on a material type?
The correct answer is C. Valuation area. See the full explanation below for the reasoning.
Question
At what level can you set quantity and value updating on a material type?
Options
- APlant
- BCompany code
- CValuation area
- DProcurement type
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C86% (24)
- D4% (1)