What information can you specify in a quota arrangement? (Choose two)

The correct answer is C. A procurement type for each source D. A quota you want to assign to the source. See the full explanation below for the reasoning.

Question

What information can you specify in a quota arrangement? (Choose two)

Options

  • AAn outline agreement number for external procurement requirements
  • BAn info record number for external procurement requirements
  • CA procurement type for each source
  • DA quota you want to assign to the source

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    11% (4)
  • C
    84% (32)