What can you specify when you assign a message schema to an application in Purchasing?

The correct answer is C. That a new message determination process is initiated for change messages. See the full explanation below for the reasoning.

Question

What can you specify when you assign a message schema to an application in Purchasing?

Options

  • AThe number of outputs for print messages
  • BThe permitted output media, for example print output or fax
  • CThat a new message determination process is initiated for change messages
  • DThe access sequence for the message types

How the community answered

(36 responses)
  • A
    14% (5)
  • B
    8% (3)
  • C
    75% (27)
  • D
    3% (1)

Community Discussion