nerdexam
SAP

C_TSCM52_64 · Question #42

Where are only time-independent conditions defined for the procurement process?

The correct answer is C. In purchase orders. See the full explanation below for the reasoning.

Question

Where are only time-independent conditions defined for the procurement process?

Options

  • AIn purchasing info records
  • BIn contracts
  • CIn purchase orders
  • DIn scheduling agreements

How the community answered

(52 responses)
  • A
    15% (8)
  • B
    8% (4)
  • C
    73% (38)
  • D
    4% (2)