SAP
C_TSCM52_64 · Question #42
Where are only time-independent conditions defined for the procurement process?
The correct answer is C. In purchase orders. See the full explanation below for the reasoning.
Question
Where are only time-independent conditions defined for the procurement process?
Options
- AIn purchasing info records
- BIn contracts
- CIn purchase orders
- DIn scheduling agreements
How the community answered
(52 responses)- A15% (8)
- B8% (4)
- C73% (38)
- D4% (2)
Community Discussion