C_TS4FI_2020 · Question #51

Which of the following are valid settlement receivers when you perform settlement for an asset under construction on a line item basis? Note: There are 2 correct answers to this question.

The correct answer is B. Cost center D. Fixed asset. See the full explanation below for the reasoning.

Question

Which of the following are valid settlement receivers when you perform settlement for an asset under construction on a line item basis? Note: There are 2 correct answers to this question.

Options

  • AFunctional area
  • BCost center
  • CProfit center
  • DFixed asset

How the community answered

(46 responses)
  • A
    7% (3)
  • B
    76% (35)
  • C
    17% (8)

Community Discussion

No community discussion yet for this question.