C_TS462_2021 · Question #77
What settings should you make to ensure precise scheduling is used when the system performs delivery scheduling? Note: There are 3 correct answers to this question.
The correct answer is B. Assign a set of working times to the plant. C. Maintain shifts defining the times for starting and ending work. E. Assign a set of working times to the shipping point. Precise scheduling in SAP SD calculates exact delivery times (hours/minutes) rather than just dates - and this requires the system to know when each location actually works. B, C, and E are correct because precise scheduling depends on a complete picture of operational hours…
Question
What settings should you make to ensure precise scheduling is used when the system performs delivery scheduling? Note: There are 3 correct answers to this question.
Options
- AMaintain the transit time in the route in hours and minutes.
- BAssign a set of working times to the plant.
- CMaintain shifts defining the times for starting and ending work.
- DAssign a shift sequence to the working times.
- EAssign a set of working times to the shipping point.
How the community answered
(22 responses)- A9% (2)
- B73% (16)
- D18% (4)
Explanation
Precise scheduling in SAP SD calculates exact delivery times (hours/minutes) rather than just dates - and this requires the system to know when each location actually works.
B, C, and E are correct because precise scheduling depends on a complete picture of operational hours: the shipping point (E) must have working times so the system knows when picking/packing/loading can occur; the plant (B) must have working times for goods issue activities; and shifts (C) are what actually define the start and end times within those working days - without shifts, working times are just calendar assignments with no time granularity.
A is wrong because transit time in hours/minutes belongs to route configuration, which affects transport duration calculation - it doesn't configure the working time framework that enables precise scheduling. D is wrong because assigning a shift sequence to working times is a production planning (PP) concept used for capacity scheduling, not the SD delivery scheduling setup.
Memory tip: Think "PSS - Plant, Shifts, Shipping point." All three must be configured together because precise scheduling can only be as granular as your least-defined location - if any one of the three is missing, the system falls back to day-based scheduling.
Topics