SAP
C_TS462_1909 · Question #77
What is the preferred Implementation methodology used in SAP S/4HANA projects?
The correct answer is B. SAP Activate. See the full explanation below for the reasoning.
Question
What is the preferred Implementation methodology used in SAP S/4HANA projects?
Options
- AASAP
- BSAP Activate
- CSAP Launch
- DWaterfall
How the community answered
(62 responses)- A3% (2)
- B73% (45)
- C8% (5)
- D16% (10)
Community Discussion