Which time elements are included in backward scheduling for a sales order? There are 2 correct answers to this question.

The correct answer is A. Transit time B. Loading time. See the full explanation below for the reasoning.

Question

Which time elements are included in backward scheduling for a sales order? There are 2 correct answers to this question.

Options

  • ATransit time
  • BLoading time
  • CShipping processing time
  • DPlanned delivery time

How the community answered

(45 responses)
  • A
    80% (36)
  • C
    7% (3)
  • D
    13% (6)