Which sales document type do you use to supply specified quantities on defined dates? Choose the correct answer.
The correct answer is D. Scheduling agreement. See the full explanation below for the reasoning.
Question
Which sales document type do you use to supply specified quantities on defined dates? Choose the correct answer.
Options
- AQuantity contract
- BValue contract
- CMaster contract
- DScheduling agreement
How the community answered
(45 responses)- A7% (3)
- B16% (7)
- C2% (1)
- D76% (34)