SAP
C_TS460_2020 · Question #72
What can you trigger in the customizing of schedule line categories? Choose Two correct answers.
The correct answer is A. Creation of a purchase requisition B. Transfer of requirements. See the full explanation below for the reasoning.
Question
What can you trigger in the customizing of schedule line categories? Choose Two correct answers.
Options
- ACreation of a purchase requisition
- BTransfer of requirements
- CProposal of the delivery date
- DImmediate creation of the delivery
How the community answered
(31 responses)- A71% (22)
- C10% (3)
- D19% (6)
Community Discussion