Your project requires a rush order process in which a delivery document is automatically created immediately after the sales order is saved. In which customizing object do you activate this? Choo…

The correct answer is A. Sales document type. See the full explanation below for the reasoning.

Question

Your project requires a rush order process in which a delivery document is automatically created immediately after the sales order is saved. In which customizing object do you activate this? Choo the correct answer.

Options

  • ASales document type
  • BSchedule line category
  • CSales item category
  • DCopy control

How the community answered

(29 responses)
  • A
    69% (20)
  • B
    21% (6)
  • C
    3% (1)
  • D
    7% (2)