SAP
C_TS460_2020 · Question #36
Your project requires shipment of several sales orders in one outbound delivery. What must the sales orders have in common? Choose Three correct answers.
The correct answer is A. Ship-to party C. Route D. Shipping point. See the full explanation below for the reasoning.
Question
Your project requires shipment of several sales orders in one outbound delivery. What must the sales orders have in common? Choose Three correct answers.
Options
- AShip-to party
- BWarehouse number
- CRoute
- DShipping point
- EPicking location
How the community answered
(40 responses)- A85% (34)
- B10% (4)
- E5% (2)
Community Discussion
No community discussion yet for this question.