nerdexam
SAP

C_TS460_1909 · Question #55

You want to use the material determination in sales orders to replace entered materials if they are not available. How can you achieve this? Please choose the correct answer.

The correct answer is D. Choose a substitution reason with the 'Automatic' substitution strategy for the material. See the full explanation below for the reasoning.

Question

You want to use the material determination in sales orders to replace entered materials if they are not available. How can you achieve this? Please choose the correct answer.

Options

  • ADeactivate the availability check in the material master and use the material determination instead
  • BAdjust the access sequence of the material determination to check the available quantities of the
  • CDeactivate the ATP check in the schedule line and activate it in the material determination record
  • DChoose a substitution reason with the 'Automatic' substitution strategy for the material

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    11% (4)
  • C
    5% (2)
  • D
    78% (29)

Community Discussion

No community discussion yet for this question.

Full C_TS460_1909 Practice