In your organizational structure, a single purchasing organization will operate across company codes. How must you assign the purchasing organization?

The correct answer is C. To the company codes for which it is responsible. When a single purchasing organization operates across multiple company codes, it must be assigned directly to each company code for which it is responsible - this cross-company-code assignment is what enables the purchasing org to procure on behalf of those entities within SAP…

Enterprise Structure and Master Data

Question

In your organizational structure, a single purchasing organization will operate across company codes. How must you assign the purchasing organization?

Options

  • ATo the plants for which it is responsible
  • BTo a standard purchasing organization
  • CTo the company codes for which it is responsible
  • DTo a reference purchasing organization

How the community answered

(36 responses)
  • A
    11% (4)
  • B
    3% (1)
  • C
    81% (29)
  • D
    6% (2)

Explanation

When a single purchasing organization operates across multiple company codes, it must be assigned directly to each company code for which it is responsible - this cross-company-code assignment is what enables the purchasing org to procure on behalf of those entities within SAP MM.

Why the distractors are wrong:

  • A is incorrect because plants are assigned to purchasing organizations (not the other way around for this setup); plant assignment is a separate, downstream step.
  • B is a distractor using SAP terminology - a "standard purchasing organization" refers to a plant-level default, not a structural assignment mechanism for cross-company scenarios.
  • D is incorrect because a reference purchasing organization is used to share conditions/contracts, not to define which company codes a purchasing org serves.

Memory tip: Think of it as jurisdiction - a purchasing org must be "authorized" by each company code it serves, so the assignment flows to the company codes. The phrase "operates across company codes" is your trigger that option C is always the answer.