Where does SAP S/4HANA store the low-level code used to determine the sequence in which materials are planned during the MRP run? Note: There are 2 correct answers to this question.

The correct answer is B. Bill of material C. MRP planning file. See the full explanation below for the reasoning.

Question

Where does SAP S/4HANA store the low-level code used to determine the sequence in which materials are planned during the MRP run? Note: There are 2 correct answers to this question.

Options

  • AProduction version
  • BBill of material
  • CMRP planning file
  • DMaterial master

How the community answered

(51 responses)
  • A
    14% (7)
  • B
    80% (41)
  • D
    6% (3)