Confirmed quantities and dates must be recorded in the purchase order item. Your purchasing department expects suppliers to send purchase order confirmations and shipping notifications. What do you…

The correct answer is C. A confirmation control key with a sequence of two confirmation types. See the full explanation below for the reasoning.

Question

Confirmed quantities and dates must be recorded in the purchase order item. Your purchasing department expects suppliers to send purchase order confirmations and shipping notifications. What do you need to configure in Customizing? Please choose the correct answer.

Options

  • AA confirmation control key with at least one confirmation type marked as relevant for planning
  • BA confirmation control key relevant for the proof of delivery
  • CA confirmation control key with a sequence of two confirmation types
  • DA purchasing value key with the order acknowledgment indicator preset

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    79% (19)
  • D
    13% (3)

Community Discussion

No community discussion yet for this question.

Full C_TS452_2021 Practice