Which of the following are features of a scheduling agreement? Note: There are 3 correct answers to this question.

The correct answer is A. A material master record is optional in a scheduling agreement item. D. A scheduling agreement item is always plant-specific. E. A scheduling agreement can be used for a consignment process. See the full explanation below for the reasoning.

Question

Which of the following are features of a scheduling agreement? Note: There are 3 correct answers to this question.

Options

  • AA material master record is optional in a scheduling agreement item.
  • BItem category M (Material unknown) can be used in a scheduling agreement.
  • CScheduling agreement delivery schedule lines can only be created manually.
  • DA scheduling agreement item is always plant-specific.
  • EA scheduling agreement can be used for a consignment process.

How the community answered

(20 responses)
  • A
    80% (16)
  • B
    15% (3)
  • C
    5% (1)