C_TS452_2021 Question #23: Real Exam Question with Answer & Explanation

The correct answer is C. The sequence of required confirmations D. Whether a confirmation is a prerequisite for a goods receipt. See the full explanation below for the reasoning.

Question

Which of the following can you control with the confirmation control key? Note: There are 2 correct answers to this question.

Options

  • ADefault reminder levels for outstanding confirmations
  • BThe document type for the goods receipt
  • CThe sequence of required confirmations
  • DWhether a confirmation is a prerequisite for a goods receipt