nerdexam
SAP

C_TS452_1909 · Question #76

Which of the following functions does the scheduling agreement with release documentation enable? There are 2 correct answers to this question.

The correct answer is B. Use release creation profiles to control the generation of forecast and Just-in-Time C. Generate both Just-in-time and forecast delivery schedules. See the full explanation below for the reasoning.

Question

Which of the following functions does the scheduling agreement with release documentation enable? There are 2 correct answers to this question.

Options

  • AGenerate Just-in-Time delivery schedules only
  • BUse release creation profiles to control the generation of forecast and Just-in-Time
  • CGenerate both Just-in-time and forecast delivery schedules
  • DGenerate forecast delivery schedules automatically using MRP

How the community answered

(45 responses)
  • A
    20% (9)
  • B
    71% (32)
  • D
    9% (4)

Community Discussion

No community discussion yet for this question.

Full C_TS452_1909 Practice