C_TS452_1909 · Question #7
How does MRP Live minimize the volume of data that must be copied from the database server to the application server and back? Please choose the correct answer. Response:
The correct answer is A. By reading all data in one database procedure. See the full explanation below for the reasoning.
Question
How does MRP Live minimize the volume of data that must be copied from the database server to the application server and back? Please choose the correct answer. Response:
Options
- ABy reading all data in one database procedure
- BBy reading only the material receipts and requirements
- CBy reading only the purchase receipts and requirements
- DBy reading only the existing purchase requisitions and planned orders
How the community answered
(20 responses)- A75% (15)
- B15% (3)
- C5% (1)
- D5% (1)