C_TS452_1909 · Question #61

What are consumption-based material requirements planning (MRP) planning procedures based on?

The correct answer is A. Previous material usage. See the full explanation below for the reasoning.

Question

What are consumption-based material requirements planning (MRP) planning procedures based on?

Options

  • APrevious material usage
  • BMaterial reservations
  • CPlanned independent requirements
  • DDependent requirements

How the community answered

(27 responses)
  • A
    70% (19)
  • B
    19% (5)
  • C
    7% (2)
  • D
    4% (1)