Which maintenance statuses must be defined in SAP Materials Management before you buy a valued material for receipt into stock? There are 2 correct answers to this question. Response:

The correct answer is A. Purchasing D. Accounting. See the full explanation below for the reasoning.

Question

Which maintenance statuses must be defined in SAP Materials Management before you buy a valued material for receipt into stock? There are 2 correct answers to this question. Response:

Options

  • APurchasing
  • BCosting
  • CStorage
  • DAccounting

How the community answered

(37 responses)
  • A
    81% (30)
  • B
    8% (3)
  • C
    11% (4)