C_TS452_1909 · Question #133

Where do you maintain the processing time for purchasing? Please choose the correct answer.

The correct answer is D. Plant parameters. See the full explanation below for the reasoning.

Question

Where do you maintain the processing time for purchasing? Please choose the correct answer.

Options

  • APurchasing view of the material master
  • BPurchasing group configuration
  • CUser parameters of the buyer
  • DPlant parameters

How the community answered

(63 responses)
  • A
    14% (9)
  • B
    5% (3)
  • C
    8% (5)
  • D
    73% (46)