SAP
C_TS452_1909 · Question #133
Where do you maintain the processing time for purchasing? Please choose the correct answer.
The correct answer is D. Plant parameters. See the full explanation below for the reasoning.
Question
Where do you maintain the processing time for purchasing? Please choose the correct answer.
Options
- APurchasing view of the material master
- BPurchasing group configuration
- CUser parameters of the buyer
- DPlant parameters
How the community answered
(63 responses)- A14% (9)
- B5% (3)
- C8% (5)
- D73% (46)
Community Discussion