For a material subject to split valuation, at which level is the price control moving average set in SAP Materials Management? Please choose the correct answer. Response:

The correct answer is A. Valuation area. See the full explanation below for the reasoning.

Question

For a material subject to split valuation, at which level is the price control moving average set in SAP Materials Management? Please choose the correct answer. Response:

Options

  • AValuation area
  • BValuation group
  • CAccount group
  • DAccount modification

How the community answered

(26 responses)
  • A
    85% (22)
  • B
    4% (1)
  • C
    8% (2)
  • D
    4% (1)