Which of the following are restrictions of material-to-material postings? There are 3 correct answers to this question.
The correct answer is A. The postings cannot be pre-planned with a reservation C. The postings can be made only from unrestricted-use stock of the issuing material to D. The postings can be made only in a single step. See the full explanation below for the reasoning.
Question
Which of the following are restrictions of material-to-material postings? There are 3 correct answers to this question.
Options
- AThe postings cannot be pre-planned with a reservation
- BThe postings can be made only between materials with the same material type
- CThe postings can be made only from unrestricted-use stock of the issuing material to
- DThe postings can be made only in a single step
- EThe postings can be made only if the stock of the issuing material is in the same storage
How the community answered
(48 responses)- A81% (39)
- B13% (6)
- E6% (3)