C_TS452_1909 · Question #101
Which of the following can be created by MRP live? There are 3 correct answers to this question.
The correct answer is A. Schedule line B. Planned order D. Purchase requisition. See the full explanation below for the reasoning.
Question
Which of the following can be created by MRP live? There are 3 correct answers to this question.
Options
- ASchedule line
- BPlanned order
- CPurchase order
- DPurchase requisition
- EMRPIist
How the community answered
(26 responses)- A77% (20)
- C8% (2)
- E15% (4)