Which of the following elements are used during forward scheduling in material requirements planning? Note: There are 2 correct Answers to this question.
The correct answer is C. Goods receipt processing time D. Purchasing processing time. See the full explanation below for the reasoning.
Question
Which of the following elements are used during forward scheduling in material requirements planning? Note: There are 2 correct Answers to this question.
Options
- AShipping processing time
- BTotal replenishment lead time
- CGoods receipt processing time
- DPurchasing processing time
How the community answered
(53 responses)- A8% (4)
- B19% (10)
- C74% (39)