nerdexam
SAP

C_TS450_2020 · Question #73

Which of the following elements are used during forward scheduling in material requirements planning? Note: There are 2 correct Answers to this question.

The correct answer is C. Goods receipt processing time D. Purchasing processing time. See the full explanation below for the reasoning.

Question

Which of the following elements are used during forward scheduling in material requirements planning? Note: There are 2 correct Answers to this question.

Options

  • AShipping processing time
  • BTotal replenishment lead time
  • CGoods receipt processing time
  • DPurchasing processing time

How the community answered

(53 responses)
  • A
    8% (4)
  • B
    19% (10)
  • C
    74% (39)

Community Discussion

No community discussion yet for this question.