Which of the following can be created by MRP Live for externally procured materials? Note: There are 2 correct Answers to this question.

The correct answer is C. Planned order D. Schedule line. See the full explanation below for the reasoning.

Question

Which of the following can be created by MRP Live for externally procured materials? Note:

There are 2 correct Answers to this question.

Options

  • AMRP list
  • BPurchase requisition
  • CPlanned order
  • DSchedule line

How the community answered