In which processes can a bill of material (BOM) be used to determine the components of a finished product? Note: There are 3 correct answer

The correct answer is B. Product costing D. Material requirements planning E. Subcontracting. See the full explanation below for the reasoning.

Question

In which processes can a bill of material (BOM) be used to determine the components of a finished product? Note: There are 3 correct answer

Options

  • AThird-party order processing
  • BProduct costing
  • CSupplier consignment
  • DMaterial requirements planning
  • ESubcontracting

How the community answered

(41 responses)
  • A
    17% (7)
  • B
    71% (29)
  • C
    12% (5)