Question
Your purchasing organization intends to procure a finished product from a supplier. The supplier will manufacture the product using components provided by your company. Which process do you use for this scenario?
Options
- AConsignment
- BThird-party
- CSubcontracting
- DExternal processing
How the community answered
(48 responses)- A8% (4)
- B2% (1)
- C85% (41)
- D4% (2)