C_TS450_2020 · Question #28
What must you do to enable the creation of Just-in-Time (JIT) delivery schedule lines for a scheduling agreement? Note: There are 2 correct Answers to this question.
The correct answer is A. Set the JIT indicator in the master record of the material used in the scheduling agreement item. B. Set the JIT Indicator field in the purchasing info record of the material and supplier used in the. See the full explanation below for the reasoning.
Question
What must you do to enable the creation of Just-in-Time (JIT) delivery schedule lines for a scheduling agreement? Note: There are 2 correct Answers to this question.
Options
- ASet the JIT indicator in the master record of the material used in the scheduling agreement item.
- BSet the JIT Indicator field in the purchasing info record of the material and supplier used in the
- CMaintain the MRP views in the master record of the material used in the scheduling agreement
- DUse a document type for the scheduling agreement for which release documentation has been
How the community answered
(23 responses)- A83% (19)
- C4% (1)
- D13% (3)
Community Discussion
No community discussion yet for this question.