SAP
C_TS450_2020 · Question #13
Where can you specify whether consumption-based planning or requirements-based planning will be performed? Note: There are 2 correct Answers to this question.
The correct answer is C. In the customizing of the plant parameters D. In the MRP area data of a material. See the full explanation below for the reasoning.
Question
Where can you specify whether consumption-based planning or requirements-based planning will be performed? Note: There are 2 correct Answers to this question.
Options
- AIn the plant data of a material
- BOn the initial screen of the planning run
- CIn the customizing of the plant parameters
- DIn the MRP area data of a material
How the community answered
(35 responses)- A11% (4)
- B6% (2)
- C83% (29)
Community Discussion
No community discussion yet for this question.