Most reports in SAP Project System can be refreshed without restarting. Which report must be restarted to update the displayed data?

The correct answer is D. Structure overview. The Structure Overview does not support dynamic refresh and must be restarted to display

Project Reporting

Question

Most reports in SAP Project System can be refreshed without restarting. Which report must be restarted to update the displayed data?

Options

  • AHierarchical reports
  • BIndividual overviews
  • CReports by cost element
  • DStructure overview

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    4% (2)
  • D
    93% (43)

Explanation

The Structure Overview does not support dynamic refresh and must be restarted to display

Topics

#structure overview#report refresh#PS report types#data update