C_TS410_2504 · Question #47

What occurs when a maintenance technician changes the status of an order to technically completed? Note: There are 3 correct answers to this question

The correct answer is B. Incoming invoices for the order can be processed C. Open purchase requisitions are marked for deletion. D. Reserved materials are released from the reservation. When a maintenance order is set to Technically Completed (TECO) in SAP PM, it signals that the physical work is done while financial/procurement activities wrap up - which is exactly why B, C, and D are correct: outstanding invoices tied to already-received goods can still be…

Enterprise Asset Management

Question

What occurs when a maintenance technician changes the status of an order to technically completed? Note: There are 3 correct answers to this question

Options

  • AA time entry is posted for the maintenance technician.
  • BIncoming invoices for the order can be processed
  • COpen purchase requisitions are marked for deletion.
  • DReserved materials are released from the reservation.
  • EThe orders settlement rule is executed.

How the community answered

(63 responses)
  • A
    10% (6)
  • B
    75% (47)
  • E
    16% (10)

Explanation

When a maintenance order is set to Technically Completed (TECO) in SAP PM, it signals that the physical work is done while financial/procurement activities wrap up - which is exactly why B, C, and D are correct: outstanding invoices tied to already-received goods can still be posted (B), open purchase requisitions are automatically flagged for deletion since no more materials are needed (C), and any reserved-but-unconsumed materials are released back to inventory (D).

Why A is wrong: Time confirmations (labor entries) must be posted before or independently of setting TECO - the status change does not auto-generate a time posting for the technician.

Why E is wrong: Settlement rule execution (transferring order costs to cost centers, assets, etc.) occurs at business completion / order closure (CLSD), not at TECO; TECO only sets the stage for settlement.

Memory tip: Think of TECO as "the wrenches are down, but the paperwork continues" - invoices flow in (B), unneeded orders go out (C), and unused stock returns (D). Settlement and time posting are separate steps that happen around TECO, not because of it.

Topics

#maintenance order#technical completion#open purchase requisitions#material reservation