What must you do in a purchase order to purchase a material for a cost center?

The correct answer is D. Enter an account assignment category. To purchase a material for a cost center in a purchase order within SAP, you must Enter an account assignment category (D). The account assignment category specifies how the purchased material or service will be charged, in this case, to a cost center. This ensures that the…

Procurement

Question

What must you do in a purchase order to purchase a material for a cost center?

Options

  • AEnter a purchase order item category
  • BEnter a storage location.
  • CEnter an activity type for the cost center in the purchasing document.
  • DEnter an account assignment category

How the community answered

(52 responses)
  • A
    13% (7)
  • B
    6% (3)
  • C
    4% (2)
  • D
    77% (40)

Explanation

To purchase a material for a cost center in a purchase order within SAP, you must Enter an account assignment category (D). The account assignment category specifies how the purchased material or service will be charged, in this case, to a cost center. This ensures that the costs are allocated correctly in the company's cost accounting records.