A customer wants to add overhead cost to a material cost estimate with quantity structure, without changing the BOM and routing. Which options does the customer have? Note: There are 2 correct…

The correct answer is A. Overhead surcharges D. Template allocation. See the full explanation below for the reasoning.

Question

A customer wants to add overhead cost to a material cost estimate with quantity structure, without changing the BOM and routing. Which options does the customer have? Note: There are 2 correct answers to this question.

Options

  • AOverhead surcharges
  • BEasy cost planning
  • CCost element planning
  • DTemplate allocation

How the community answered

(48 responses)
  • A
    79% (38)
  • B
    13% (6)
  • C
    8% (4)