SAP
C_TPLM30_67 · Question #82
What happens when you set the system status in a maintenance order to technically completed (TECO)? (Choose two)
The correct answer is A. The system sets a deletion indicator for outstanding reservations. B. The system sets a deletion indicator for outstanding purchase requisitions. See the full explanation below for the reasoning.
Question
What happens when you set the system status in a maintenance order to technically completed (TECO)? (Choose two)
Options
- AThe system sets a deletion indicator for outstanding reservations.
- BThe system sets a deletion indicator for outstanding purchase requisitions.
- CThe system posts costs to the target account assignment.
- DThe system sets a deletion indicator for purchase orders assigned to the maintenance order.
How the community answered
(44 responses)- A84% (37)
- C11% (5)
- D5% (2)
Community Discussion
No community discussion yet for this question.