What does the scheduling period determine in the maintenance plan scheduling parameters?
The correct answer is B. The duration for which the system generates planned or call dates during scheduling. See the full explanation below for the reasoning.
Question
What does the scheduling period determine in the maintenance plan scheduling parameters?
Options
- AThe duration for which the system generates maintenance orders immediately
- BThe duration for which the system generates planned or call dates during scheduling
- CThe duration for which the system generates maintenance notifications immediately
- DThe validity period of the maintenance plan
How the community answered
(34 responses)- A3% (1)
- B85% (29)
- C9% (3)
- D3% (1)
Community Discussion
No community discussion yet for this question.