Your customer plans a plant shutdown and wants to use the Maintenance Event Builder to plan revisions and create maintenance orders automatically. What must you do in Customizing?
The correct answer is C. Create a revision type and select WPS-Controlled. See the full explanation below for the reasoning.
Question
Your customer plans a plant shutdown and wants to use the Maintenance Event Builder to plan revisions and create maintenance orders automatically. What must you do in Customizing?
Options
- ADefine field values for PM/PS Reference Element
- BDefine transfer of project or investment program
- CCreate a revision type and select WPS-Controlled.
- DCreate a revision type and select Not WPS-Controlled.
How the community answered
(32 responses)- A3% (1)
- B6% (2)
- C78% (25)
- D13% (4)
Community Discussion