C_TPLM30_67 · Question #52
Your customer uses operating hours to execute a performance-based maintenance plan. Which of the following data must you assign in the maintenance plan header?
The correct answer is B. A cycle unit of measure with a corresponding characteristic from the measuring point. See the full explanation below for the reasoning.
Question
Your customer uses operating hours to execute a performance-based maintenance plan. Which of the following data must you assign in the maintenance plan header?
Options
- AA task list for performance-based maintenance
- BA cycle unit of measure with a corresponding characteristic from the measuring point
- CAn order type for performance-based maintenance
- DA technical object with a measuring point
How the community answered
(39 responses)- A5% (2)
- B85% (33)
- C8% (3)
- D3% (1)