C_TPLM30_67 · Question #50
What are the prerequisites for creating a capacity requirement in a maintenance order operation? (Choose two)
The correct answer is C. The numeric value for Work in the order operation must be greater than 0. D. The operation must have a control key with the Determine Capacity Requirements indicator set. See the full explanation below for the reasoning.
Question
What are the prerequisites for creating a capacity requirement in a maintenance order operation? (Choose two)
Options
- AThe performing work center must have available capacity data.
- BThe performing work center must have a control key with the Determine Capacity Requirements
- CThe numeric value for Work in the order operation must be greater than 0.
- DThe operation must have a control key with the Determine Capacity Requirements indicator set.
How the community answered
(52 responses)- A6% (3)
- B10% (5)
- C85% (44)