C_TPLM30_67 · Question #43
A maintenance plan has a completion requirement. The plan contains five maintenance items that produce five notifications. Which system status must each notification have before the maintenance call…
The correct answer is D. NOCO (Notification Completed). See the full explanation below for the reasoning.
Question
A maintenance plan has a completion requirement. The plan contains five maintenance items that produce five notifications. Which system status must each notification have before the maintenance call is completed and the next maintenance call can be generated?
Options
- AREL (Released)
- BATCO (All Tasks Completed)
- CTECO (Technically Completed)
- DNOCO (Notification Completed)
How the community answered
(39 responses)- A5% (2)
- B3% (1)
- C8% (3)
- D85% (33)