How are the planned costs for the refurbished part or parts displayed in the planned/actual order report?

The correct answer is A. As costs with a negative value. See the full explanation below for the reasoning.

Question

How are the planned costs for the refurbished part or parts displayed in the planned/actual order report?

Options

  • AAs costs with a negative value
  • BAs costs with a positive value
  • CAs revenue with a negative value
  • DAs revenue with a positive value

How the community answered

(33 responses)
  • A
    73% (24)
  • B
    9% (3)
  • C
    15% (5)
  • D
    3% (1)