C_TPLM30_67 · Question #187
How are the planned costs for the refurbished part or parts displayed in the planned/actual order report?
The correct answer is A. As costs with a negative value. See the full explanation below for the reasoning.
Question
How are the planned costs for the refurbished part or parts displayed in the planned/actual order report?
Options
- AAs costs with a negative value
- BAs costs with a positive value
- CAs revenue with a negative value
- DAs revenue with a positive value
How the community answered
(33 responses)- A73% (24)
- B9% (3)
- C15% (5)
- D3% (1)