C_TPLM30_67 · Question #182

What does the scheduling period determine in the maintenance plan scheduling parameters? Please choose the correct answer. Response:

The correct answer is B. The duration for which the system generates planned or call dates during scheduling. See the full explanation below for the reasoning.

Question

What does the scheduling period determine in the maintenance plan scheduling parameters? Please choose the correct answer. Response:

Options

  • AThe duration for which the system generates maintenance orders immediately
  • BThe duration for which the system generates planned or call dates during scheduling
  • CThe duration for which the system generates maintenance notifications immediately
  • DThe validity period of the maintenance plan

How the community answered

(42 responses)
  • A
    12% (5)
  • B
    79% (33)
  • C
    5% (2)
  • D
    5% (2)