What happens when you set the system status in a maintenance order to technically completed (TECO)? There are 2 correct answers to this question. Response:

The correct answer is A. The system sets a deletion indicator for outstanding reservations. B. The system sets a deletion indicator for outstanding purchase requisitions. See the full explanation below for the reasoning.

Question

What happens when you set the system status in a maintenance order to technically completed (TECO)? There are 2 correct answers to this question. Response:

Options

  • AThe system sets a deletion indicator for outstanding reservations.
  • BThe system sets a deletion indicator for outstanding purchase requisitions.
  • CThe system posts costs to the target account assignment.
  • DThe system sets a deletion indicator for purchase orders assigned to the maintenance order.

How the community answered

(23 responses)
  • A
    74% (17)
  • C
    17% (4)
  • D
    9% (2)