Your customer wants to utilize estimated costs in Plant Maintenance orders. Which condition does the customer need to be aware of? Please choose the correct answer. Response:

The correct answer is D. Upon release of the order, estimated costs cannot be revised. See the full explanation below for the reasoning.

Question

Your customer wants to utilize estimated costs in Plant Maintenance orders. Which condition does the customer need to be aware of? Please choose the correct answer. Response:

Options

  • APlanned costs overwrite estimated costs after release of the order.
  • BA specific order type in which cost estimates are activated must be used.
  • CPlanned costs must not exceed the estimated costs.
  • DUpon release of the order, estimated costs cannot be revised.

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    9% (2)
  • C
    13% (3)
  • D
    74% (17)