Your customer executes deadline monitoring (transaction IP30). What happens after you insert additional call dates using the manual call function? Please choose the correct answer. Response:
The correct answer is B. The system retains the normal scheduled call dates. See the full explanation below for the reasoning.
Question
Your customer executes deadline monitoring (transaction IP30). What happens after you insert additional call dates using the manual call function? Please choose the correct answer. Response:
Options
- AThe system restarts the maintenance plan.
- BThe system retains the normal scheduled call dates.
- CThe system fixes the next scheduled call date.
- DThe system reschedules all previous scheduled call dates.
How the community answered
(63 responses)- A3% (2)
- B75% (47)
- C14% (9)
- D8% (5)