SAP
C_TPLM30_67 · Question #135
A maintenance technician replaces a defective counter with a new counter. Before the users can create a standard measuring document for the new counter, what step(s) must they perform? Please choose…
The correct answer is B. Create a special measuring document and set the Counter Replacement indicator. See the full explanation below for the reasoning.
Question
A maintenance technician replaces a defective counter with a new counter. Before the users can create a standard measuring document for the new counter, what step(s) must they perform? Please choose the correct answer. Response:
Options
- ACreate a new technical object to represent the new measuring point.
- BCreate a special measuring document and set the Counter Replacement indicator.
- CDismantle the old measuring point and create a new measuring point.
- DCreate a new measuring point and change the measuring point from which the measurement
How the community answered
(34 responses)- A6% (2)
- B71% (24)
- C15% (5)
- D9% (3)
Community Discussion
No community discussion yet for this question.