C_TPLM30_67 · Question #129

Your customer wants to assign maintenance orders to network activities automatically with the Maintenance Event Builder (MEB). Which of the following steps must you perform? There are 2 correct…

The correct answer is C. Assign a network to a revision with revision type WPS-controlled. E. Assign the Reference PM/PS element to task list headers and network activities. See the full explanation below for the reasoning.

Question

Your customer wants to assign maintenance orders to network activities automatically with the Maintenance Event Builder (MEB). Which of the following steps must you perform? There are 2 correct answers to this question. Response:

Options

  • ASet the define Transfer of Project or Invest Program indicator.
  • BAssign maintenance orders manually to a revision with revision type WPS-controlled.
  • CAssign a network to a revision with revision type WPS-controlled.
  • DAssign a hierarchical task list to a notification.
  • EAssign the Reference PM/PS element to task list headers and network activities.

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    15% (4)
  • C
    70% (19)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.